Part of the £240 million New Waverley regeneration in Edinburgh’s Old Town, this 276-bed development is a 10-minute walk from the University of Edinburgh.
Scope of Works
McAleer & Rushe appointed Project ff&e to supply and install furniture throughout the PBSA development.
The FF&E package covered fixed and loose furniture in 267 studios and 3 townhouses. Each studio was completed with bedroom furniture and its own kitchen, including appliances, whilst each townhouse included a complete furniture package across 3 bedrooms and a communal kitchen. We also furnished the parcel store, the staff kitchen and the back-of-house kitchen.
Programme and Delivery
The contracting team was on site for around 24 weeks between November 2025 and September 2026. A site manager, four labourers and four fitters installed 20–22 rooms a week at first fix.
Challenges and Solutions
Edinburgh’s high winds often stopped the crane, which cut down our time to offload deliveries. We worked around this by adjusting our programme to make the most of the calmer days, which kept installation running even when the crane was down.
Local employment
Our labour, fitters and site management were all recruited locally, keeping skills and employment in Edinburgh.
Project Outcome
New Waverley demonstrates Project ff&e’s ability to deliver a substantial furniture supply and installation package within a complex construction environment. Despite logistical challenges, our focus on workmanship, safety, productivity and collaboration with other trades helped us maintain a steady rate of progress and contribute positively to this significant Edinburgh development.
Client: Vita Student
Main Contractor: McAleer & Rushe
Architect: CDA